PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 9501
CONTRACT: Lake Street Sanitary Sewer Replacement - 2024
Percentage of Contract Completed:
94.86%
|
Associated Projects:
- Lake Street Sanitary Sewer Replacement - 2024 (15045)
|
PROJECT: |
Lake Street Sanitary Sewer Replacement - 2024 |
Project Number: |
15045 |
Bid Due Date: |
04/04/24
|
Bid Open Date: |
04/04/2024 |
Estimated Start Date: |
06/15/2024
|
Estimated Completion Date: |
08/30/2024
|
Percent of Project Completed: |
94.86 %
|
Contract Amount: |
$1,412,900.00
|
Project Contractor: |
RG HUSTON COMPANY INC
|
Construction Year: |
2024 |
Construction Type: |
|
District: |
|
PROJECT CONTACT: |
Project Manager: |
Kyle Frank |
Phone: |
608-266-4098 |
Email: |
kfrank@cityofmadison.com |
Inspector: |
Beer, Shawn |
Phone: |
608-219-8165 |
Documents & Specs
|