PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 9605
CONTRACT: Prairie Hills Detention Basin Improvements
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- Prairie Hills Detention Basin Improvements (14915)
|
PROJECT: |
Prairie Hills Detention Basin Improvements |
Project Number: |
14915 |
Bid Due Date: |
11/14/24
|
Bid Open Date: |
11/14/2024 |
Estimated Start Date: |
02/03/2025
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$390,871.10
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2024 |
Construction Type: |
Storm |
District: |
07,
|
PROJECT CONTACT: |
Project Manager: |
Grant Pokos |
Phone: |
608-266-4862 |
Email: |
gpokos@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|