PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6590
CONTRACT: Construction of Fire Station #13
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Fire Station #13 (53W1152)
|
PROJECT: |
Fire Station #13 |
Project Number: |
53W1152 |
Bid Due Date: |
05/27/13
|
Bid Open Date: |
05/24/2013 |
Estimated Start Date: |
09/11/2013
|
Estimated Completion Date: |
05/09/2014
|
Percent of Project Completed: |
100.0 %
|
Contract Amount: |
$4,055,690.00
|
Project Contractor: |
MIRON CONSTRUCTION CO INC
|
Construction Year: |
2014 |
Construction Type: |
Facilities |
District: |
03,
|
PROJECT CONTACT: |
Project Manager: |
Randy Wiesner |
Phone: |
608-267-8679 |
Email: |
rwiesner@cityofmadison.com |
Inspector: |
Whitney, James |
Phone: |
(608) 266-4563 |
Documents & Specs
|