CONTRACT NUMBER: 6994
CONTRACT: Livingston Street Resurfacing with Utilities
Percentage of Contract Completed:
92.7%
|
Associated Projects:
- Livingston Street Resurfacing with Utilities (53W1462)
|
| PROJECT: |
Livingston Street Resurfacing with Utilities |
| Project Number: |
53W1462 |
| Bid Due Date: |
01/11/13
|
| Bid Open Date: |
01/18/2013 |
| Estimated Start Date: |
03/11/2013
|
| Estimated Completion Date: |
07/12/2013
|
| Percent of Project Completed: |
92.7 %
|
| Contract Amount: |
$912,287.58
|
| Project Contractor: |
CAPITOL UNDERGROUND INC
|
| Construction Year: |
2013 |
| Construction Type: |
Street |
| District: |
02,
|
|
PROJECT CONTACT: |
| Project Manager: |
Eric Dundee |
| Phone: |
608-266-4913 |
| Email: |
edundee@cityofmadison.com |
| Inspector: |
Lauby, Paul |
| Phone: |
520-2378 |