PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7239
CONTRACT: Chip Sealing 2014-East
Percentage of Contract Completed:
96.6%
|
Associated Projects:
- Chip Sealing 2014-East (53W1714)
|
PROJECT: |
Chip Sealing 2014-East |
Project Number: |
53W1714 |
Bid Due Date: |
02/21/14
|
Bid Open Date: |
02/21/2014 |
Estimated Start Date: |
04/14/2014
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
96.6 %
|
Contract Amount: |
$337,822.50
|
Project Contractor: |
SCOTT CONSTRUCTION INC
|
Construction Year: |
2014 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|