CONTRACT NUMBER: 7896
CONTRACT: Chippewa Drive Sidewalk Assessment District -2017
Percentage of Contract Completed: 99.9%
Associated Projects:
  • 2017-New Sidewalk Installation (11571)
PROJECT: 2017-New Sidewalk Installation
Project Number: 11571
Bid Due Date: 08/11/17
Bid Open Date: 08/11/2017
Estimated Start Date: 10/16/2017
Estimated Completion Date: 10/13/2017
Percent of Project Completed: 99.9 %
Contract Amount: $48,356.25
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2017
Construction Type: Sidewalk
District: 06, 10, 17,
PROJECT CONTACT:
Project Manager: Chris Dawson
Phone: 261-5537
Email: cdawson@cityofmadison.com
Inspector: Mael, Stewart
Phone: 261-9695