CONTRACT NUMBER: 7901
CONTRACT: Demetral Park Path Phase 2
Percentage of Contract Completed: 81.18%
Associated Projects:
  • Demetral Park Path Phase 2 (11515)
PROJECT: Demetral Park Path Phase 2
Project Number: 11515
Bid Due Date: 07/08/21
Bid Open Date: 07/08/2021
Estimated Start Date: 09/07/2021
Estimated Completion Date: 10/21/2021
Percent of Project Completed: 81.18 %
Contract Amount: $397,518.32
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2021
Construction Type: Bike Path
District: 12,
PROJECT CONTACT:
Project Manager: Aaron Canton
Phone: (608) 242-4763
Email: acanton@cityofmadison.com
Inspector: Lauby, Paul
Phone: