PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8583
CONTRACT: Halo Lane and Twilight Trail Reconstruction
Percentage of Contract Completed:
78.42%
|
Associated Projects:
- Halo Lane and Twilight Trail Reconstruction (13011)
|
PROJECT: |
Halo Lane and Twilight Trail Reconstruction |
Project Number: |
13011 |
Bid Due Date: |
02/09/23
|
Bid Open Date: |
02/09/2023 |
Estimated Start Date: |
04/11/2023
|
Estimated Completion Date: |
05/19/2023
|
Percent of Project Completed: |
78.42 %
|
Contract Amount: |
$283,844.50
|
Project Contractor: |
Parisi Construction LLC
|
Construction Year: |
2023 |
Construction Type: |
Street |
District: |
16,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|