PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8642
CONTRACT: West Towne Path - Phase 3
Percentage of Contract Completed:
94.32%
|
Associated Projects:
- West Towne Path - Phase 3 (13014)
|
PROJECT: |
West Towne Path - Phase 3 |
Project Number: |
13014 |
Bid Due Date: |
04/06/23
|
Bid Open Date: |
04/06/2023 |
Estimated Start Date: |
06/05/2023
|
Estimated Completion Date: |
08/15/2023
|
Percent of Project Completed: |
94.32 %
|
Contract Amount: |
$899,099.00
|
Project Contractor: |
Parisi Construction LLC
|
Construction Year: |
2023 |
Construction Type: |
Street |
District: |
01,
|
PROJECT CONTACT: |
Project Manager: |
Aaron Canton |
Phone: |
(608) 242-4763 |
Email: |
acanton@cityofmadison.com |
Inspector: |
Belohlavek, Rachel |
Phone: |
608-7836 |