PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8657
CONTRACT: Safe Streets Madison 2022-Group 1 (rebid)
Percentage of Contract Completed:
89.22%
|
Associated Projects:
- Safe Streets Madison 2022 (13923)
|
PROJECT: |
Safe Streets Madison 2022 |
Project Number: |
13923 |
Bid Due Date: |
07/07/22
|
Bid Open Date: |
07/07/2022 |
Estimated Start Date: |
04/03/2023
|
Estimated Completion Date: |
05/31/2023
|
Percent of Project Completed: |
89.22 %
|
Contract Amount: |
$955,256.19
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2022 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Jim Wolfe |
Phone: |
608-266-4099 |
Email: |
jwolfe@cityofmadison.com |
Inspector: |
Ledden, Jason |
Phone: |
608-264-7430 |
Documents & Specs
|