PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6833
CONTRACT: Burrows Park Shoreline
Percentage of Contract Completed:
91.3%
|
Associated Projects:
- Burrows Park Shoreline (53W1374)
|
| PROJECT: |
Burrows Park Shoreline |
| Project Number: |
53W1374 |
| Bid Due Date: |
10/12/12
|
| Bid Open Date: |
10/12/2012 |
| Estimated Start Date: |
12/03/2012
|
| Estimated Completion Date: |
12/12/2012
|
| Percent of Project Completed: |
91.3 %
|
| Contract Amount: |
$39,626.20
|
| Project Contractor: |
BADGERLAND EXCAVATING CORP
|
| Construction Year: |
2012 |
| Construction Type: |
Storm |
| District: |
12,
|
|
PROJECT CONTACT: |
| Project Manager: |
Lisa Coleman |
| Phone: |
608-266-4093 |
| Email: |
lcoleman@cityofmadison.com |
| Inspector: |
Lauby, Paul |
| Phone: |
520-2378 |
Documents & Specs
|