CONTRACT: Park Street Pedestrian Bridge Repair
Percentage of Contract Completed: 91.1%
Associated Projects:
  • Park Street Pedestrian Bridge Repair (53W1302)
PROJECT: Park Street Pedestrian Bridge Repair
Project Number: 53W1302
Bid Due Date: 09/14/12
Bid Open Date: 09/14/2012
Estimated Start Date: 10/23/2012
Estimated Completion Date: 11/09/2012
Percent of Project Completed: 91.1 %
Contract Amount: $19,849.02
Project Contractor: JOE DANIELS CONSTRUCTION CO INC
Construction Year: 2012
Construction Type: Bridge
District: 13,
PROJECT CONTACT:
Project Manager: Glen Yoerger
Phone: 608-261-9177
Email: gyoerger@cityofmadison.com
Inspector: Ziegler-Henderson, Lauri
Phone: 261-5585