PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7030
CONTRACT: Forest Hill Cemetery- Masonry Repairs to the Receiving Vault
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Forest Hill Cemetery- Masonry Repairs to the Receiving Vault
& Chapel, Roof Replacement for the Chappel (53W1573)
|
PROJECT: |
Forest Hill Cemetery- Masonry Repairs to the Receiving Vault
& Chapel, Roof Replacement for the Chappel |
Project Number: |
53W1573 |
Bid Due Date: |
04/26/13
|
Bid Open Date: |
04/26/2013 |
Estimated Start Date: |
06/17/2013
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
100.0 %
|
Contract Amount: |
$143,785.00
|
Project Contractor: |
JOE DANIELS CONSTRUCTION CO INC
|
Construction Year: |
2013 |
Construction Type: |
Facilities |
District: |
13,
|
PROJECT CONTACT: |
Project Manager: |
Paul Stauffer |
Phone: |
608-266-4366 |
Email: |
pstauffer@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|