PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7901
CONTRACT: Demetral Park Path Phase 2
Percentage of Contract Completed:
81.18%
|
Associated Projects:
- Demetral Park Path Phase 2 (11515)
|
| PROJECT: |
Demetral Park Path Phase 2 |
| Project Number: |
11515 |
| Bid Due Date: |
07/08/21
|
| Bid Open Date: |
07/08/2021 |
| Estimated Start Date: |
09/07/2021
|
| Estimated Completion Date: |
10/21/2021
|
| Percent of Project Completed: |
81.18 %
|
| Contract Amount: |
$397,518.32
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2021 |
| Construction Type: |
Bike Path |
| District: |
12,
|
|
PROJECT CONTACT: |
| Project Manager: |
Aaron Canton |
| Phone: |
(608) 242-4763 |
| Email: |
acanton@cityofmadison.com |
| Inspector: |
Lauby, Paul |
| Phone: |
520-2378 |
Documents & Specs
|