CONTRACT NUMBER: 8041
CONTRACT: CIPP Rehab of Large Diameter Storm Sewer
Percentage of Contract Completed:
81.02%
|
Associated Projects:
- CIPP Rehab of Large Diameter Storm Sewer (11728)
|
| PROJECT: |
CIPP Rehab of Large Diameter Storm Sewer |
| Project Number: |
11728 |
| Bid Due Date: |
09/08/17
|
| Bid Open Date: |
09/08/2017 |
| Estimated Start Date: |
10/30/2017
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
81.02 %
|
| Contract Amount: |
$182,893.30
|
| Project Contractor: |
MICHELS CORPORATION
|
| Construction Year: |
2017 |
| Construction Type: |
Storm |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
Kyle Frank |
| Phone: |
608-266-4098 |
| Email: |
kfrank@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|