PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6990
CONTRACT: Chip Sealing 2013-West
Percentage of Contract Completed:
90.5%
|
Associated Projects:
- Chip Sealing 2013-West (53W1482)
|
| PROJECT: |
Chip Sealing 2013-West |
| Project Number: |
53W1482 |
| Bid Due Date: |
04/05/13
|
| Bid Open Date: |
04/12/2013 |
| Estimated Start Date: |
05/28/2013
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
90.5 %
|
| Contract Amount: |
$424,829.57
|
| Project Contractor: |
SCOTT CONSTRUCTION INC
|
| Construction Year: |
2013 |
| Construction Type: |
Street |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
Steve Sonntag |
| Phone: |
608-267-1997 |
| Email: |
ssonntag@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|