PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7228
CONTRACT: Alley Reconstruction, Block 11 Bowens addition
Percentage of Contract Completed:
92.3%
|
Associated Projects:
- Alley Reconstruction, Block 11 Bowens addition (53W1583)
|
PROJECT: |
Alley Reconstruction, Block 11 Bowens addition |
Project Number: |
53W1583 |
Bid Due Date: |
06/20/14
|
Bid Open Date: |
06/20/2014 |
Estimated Start Date: |
08/20/2014
|
Estimated Completion Date: |
10/15/2014
|
Percent of Project Completed: |
92.3 %
|
Contract Amount: |
$129,823.50
|
Project Contractor: |
BADGERLAND EXCAVATING CORP
|
Construction Year: |
2014 |
Construction Type: |
Street |
District: |
13,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Ziegler-Henderson, Lauri |
Phone: |
261-5585 |
Documents & Specs
|