PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7245
CONTRACT: Capital City Path Reconstruction and Bridge Replacement
Percentage of Contract Completed:
98.7%
|
Associated Projects:
- Capital City Path Reconstruction and Bridge Replacement (53W1704)
|
| PROJECT: |
Capital City Path Reconstruction and Bridge Replacement |
| Project Number: |
53W1704 |
| Bid Due Date: |
04/24/15
|
| Bid Open Date: |
04/24/2015 |
| Estimated Start Date: |
07/20/2015
|
| Estimated Completion Date: |
10/30/2015
|
| Percent of Project Completed: |
98.7 %
|
| Contract Amount: |
$952,219.80
|
| Project Contractor: |
HOMBURG CONTRACTORS INC
|
| Construction Year: |
2015 |
| Construction Type: |
Bike Path |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
Tony Fernandez |
| Phone: |
608-266-9219 |
| Email: |
afernandez@cityofmadison.com |
| Inspector: |
Hoel, Eric |
| Phone: |
|
Documents & Specs
|