PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7274
CONTRACT: Breese Stevens Field SyntheticTurf - 2014
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- Breese Stevens Field Synthetic Turf - 2014 (53W1757)
|
| PROJECT: |
Breese Stevens Field Synthetic Turf - 2014 |
| Project Number: |
53W1757 |
| Bid Due Date: |
05/23/14
|
| Bid Open Date: |
05/23/2014 |
| Estimated Start Date: |
08/04/2014
|
| Estimated Completion Date: |
10/17/2014
|
| Percent of Project Completed: |
Not Available
|
| Contract Amount: |
$729,843.15
|
| Project Contractor: |
H & H CIVIL CONSTRUCTION LLC
|
| Construction Year: |
2014 |
| Construction Type: |
Facilities |
| District: |
02,
|
|
PROJECT CONTACT: |
| Project Manager: |
Tom Maglio |
| Phone: |
608-266-6518 |
| Email: |
tmaglio@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|