PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7444
CONTRACT: Local Road Traffic Calming & Arterial Ped Enhancements-2015
Percentage of Contract Completed:
103.2%
|
Associated Projects:
- Local Road Traffic Calming & Arterial Ped Enhancements-2015 (53W1882)
|
PROJECT: |
Local Road Traffic Calming & Arterial Ped Enhancements-2015 |
Project Number: |
53W1882 |
Bid Due Date: |
05/08/15
|
Bid Open Date: |
05/08/2015 |
Estimated Start Date: |
07/10/2015
|
Estimated Completion Date: |
10/02/2015
|
Percent of Project Completed: |
103.2 %
|
Contract Amount: |
$164,062.00
|
Project Contractor: |
RAYMOND P CATTELL INC
|
Construction Year: |
2015 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Jim Wolfe |
Phone: |
608-266-4099 |
Email: |
jwolfe@cityofmadison.com |
Inspector: |
Schlotthauer, Bill |
Phone: |
266-4088 |
Documents & Specs
|