PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7869
CONTRACT: Library Maintenance & Support Center HAZMAT Abatement
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Library Maintenance & Support Center Remodel (10001)
|
| PROJECT: |
Library Maintenance & Support Center Remodel |
| Project Number: |
10001 |
| Bid Due Date: |
02/10/17
|
| Bid Open Date: |
02/10/2017 |
| Estimated Start Date: |
03/27/2017
|
| Estimated Completion Date: |
04/21/2017
|
| Percent of Project Completed: |
100.0 %
|
| Contract Amount: |
$19,768.24
|
| Project Contractor: |
DIRTY DUCTS CLEAINING, ENVIRONMENTAL & INSULATION INC
|
| Construction Year: |
|
| Construction Type: |
|
| District: |
14,
|
|
PROJECT CONTACT: |
| Project Manager: |
|
| Phone: |
|
| Email: |
|
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|