PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8000
CONTRACT: E. Gilman St and N. Pinckney St Resurfacing
Percentage of Contract Completed:
91.5%
|
Associated Projects:
- E. Gilman St, N. Pinckney St and N. Bultler St Resurfacing w/Utilities (11649)
|
PROJECT: |
E. Gilman St, N. Pinckney St and N. Bultler St Resurfacing w/Utilities |
Project Number: |
11649 |
Bid Due Date: |
09/22/17
|
Bid Open Date: |
09/22/2017 |
Estimated Start Date: |
04/02/2018
|
Estimated Completion Date: |
06/30/2018
|
Percent of Project Completed: |
91.5 %
|
Contract Amount: |
$1,462,066.58
|
Project Contractor: |
S & L Underground, Inc.
|
Construction Year: |
2018 |
Construction Type: |
Street |
District: |
02,
|
PROJECT CONTACT: |
Project Manager: |
Christy Bachmann |
Phone: |
608-266-4095 |
Email: |
cbachmann@cityofmadison.com |
Inspector: |
Armstrong, Steve |
Phone: |
266-4914 |
Documents & Specs
|