CONTRACT NUMBER: 8460
CONTRACT: Sauk Creek Greenway - Tree Lane to High Point
Percentage of Contract Completed: 89.59%
Associated Projects:
  • Sauk Creek Greenway - Tree Lane to High Point (10985)
PROJECT: Sauk Creek Greenway - Tree Lane to High Point
Project Number: 10985
Bid Due Date: 08/08/19
Bid Open Date: 08/08/2019
Estimated Start Date: 09/30/2019
Estimated Completion Date: 10/31/2019
Percent of Project Completed: 89.59 %
Contract Amount: $268,486.15
Project Contractor: S & L Underground, Inc.
Construction Year: 2019
Construction Type: Storm
District:
PROJECT CONTACT:
Project Manager: JoJo O'Brien
Phone: (608)266-9721
Email: JOBrien@cityofmadison.com
Inspector: Mael, Stewart
Phone: 261-9695


Documents & Specs