PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8461
CONTRACT: CIPP Rehab of Sanitary and Storm Sewers-2019
Percentage of Contract Completed:
99.70%
|
Associated Projects:
- CIPP Rehab of Sanitary and Storm Sewers - 2019 (11989)
|
PROJECT: |
CIPP Rehab of Sanitary and Storm Sewers - 2019 |
Project Number: |
11989 |
Bid Due Date: |
08/08/19
|
Bid Open Date: |
08/08/2019 |
Estimated Start Date: |
09/16/2019
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
99.70 %
|
Contract Amount: |
$1,135,625.90
|
Project Contractor: |
VISU-SEWER, LLC
|
Construction Year: |
2019 |
Construction Type: |
Sanitary |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Kyle Frank |
Phone: |
608-266-4098 |
Email: |
kfrank@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|