PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8535
CONTRACT: Metro Transit Phase 2 - HVAC Replacement
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Metro Transit E. Wash Upgrades (11229)
|
PROJECT: |
Metro Transit E. Wash Upgrades |
Project Number: |
11229 |
Bid Due Date: |
02/06/20
|
Bid Open Date: |
02/06/2020 |
Estimated Start Date: |
03/30/2020
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
100.0 %
|
Contract Amount: |
$4,650,660.00
|
Project Contractor: |
Kenneth F. Sullivan Co.
|
Construction Year: |
2021 |
Construction Type: |
Facilities |
District: |
06,
|
PROJECT CONTACT: |
Project Manager: |
Jon Evans |
Phone: |
243-5893 |
Email: |
jevans@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|