CONTRACT NUMBER: 8560
CONTRACT: West Transfer Point Concrete Joint Repair 2020
Percentage of Contract Completed:
85.46%
|
Associated Projects:
- West Transfer Point Concrete Joint Repair 2020 (85100X)
|
PROJECT: |
West Transfer Point Concrete Joint Repair 2020 |
Project Number: |
85100X |
Bid Due Date: |
06/25/20
|
Bid Open Date: |
06/25/2020 |
Estimated Start Date: |
08/17/2020
|
Estimated Completion Date: |
09/01/2020
|
Percent of Project Completed: |
85.46 %
|
Contract Amount: |
$67,095.00
|
Project Contractor: |
Bachmann Construction
|
Construction Year: |
2020 |
Construction Type: |
Misc |
District: |
19,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Ledden, Jason |
Phone: |
608-264-7430 |
Documents & Specs
|