PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7407
CONTRACT: Jenifer, Paterson & Brearly St Reconstruction & Few St(resurfacing)
Percentage of Contract Completed:
94.9%
|
Associated Projects:
- Jenifer, Paterson & Brearly St Reconstruction & Few St(resurfacing) (53W1507)
|
| PROJECT: |
Jenifer, Paterson & Brearly St Reconstruction & Few St(resurfacing) |
| Project Number: |
53W1507 |
| Bid Due Date: |
04/08/16
|
| Bid Open Date: |
04/08/2016 |
| Estimated Start Date: |
05/23/2016
|
| Estimated Completion Date: |
10/31/2016
|
| Percent of Project Completed: |
94.9 %
|
| Contract Amount: |
$3,462,702.71
|
| Project Contractor: |
Capitol Underground
|
| Construction Year: |
2016 |
| Construction Type: |
Street |
| District: |
06,
|
|
PROJECT CONTACT: |
| Project Manager: |
Lisa Coleman |
| Phone: |
608-266-4093 |
| Email: |
lcoleman@cityofmadison.com |
| Inspector: |
Ziegler-Henderson, Lauri |
| Phone: |
261-5585 |
Documents & Specs
|