Old Middleton Road construction will be completed by the end of October 2022

September 2, 2022 8:14 AM

Why Old Middleton ROAD Needed To Be Reconstructed?

Existing conditions of City owned infrastructure along Old Middleton Rd were poor and required replacement in order for the road to perform efficiently. Some of reasons why this road needed a reconstruction are:

  • ?Construction work on Old Middleton Road 9-1-2022?
    Old Middleton Road 9/1/22
    The average pavement throughout Old Middleton Rd had an average rating 4 out of 10. A rating of 4 means a poor quality condition for pavements in the City.
  • The sanitary sewer main and laterals were installed in the 1940's and 1950's, the material was clay, and video evidence showed multiple sections of sewer that were broken and not draining sewerage properly. 
  • Lack of storm sewer pipes and drains throughout the project limits were causing drainage issues after big rain events.
  • Pedestrian facilities such as sidewalks and ramps at various locations throughout the road that did not meet the Americans with Disabilities Act Guidelines nor the City of Madison Standards.
  • Sections of concrete curb and gutter that were broken or had vertical deflections causing poor drainage conditions.
  • Lack of safety features for bicyclist throughout the Old Middleton Rd corridor.

 

Construction of Proposed Improvement and Impacts

? Construction work on Old Middleton Road 9-1-2022
Old Middleton Road 9/1/22

The limits of the overall project are Old Middleton Rd from N Eau Claire Ave to Capital Ave. The project is divided in two segments, east and west. The east segment is from N Eau Claire Ave to Old Sauk Rd and the west segment is from Old Sauk Rd to Capital Ave. Construction on the east segment started in April will be completed by the end of October while construction on the west segment started in June and will be completed by the end of September.

The City recognized the importance of maintaining vehicular access on the east segment as it has businesses and residences connected to it. One way traffic on the westbound direction has been maintained throughout the project duration from N Eau Claire Ave to N Rosa Rd and two way traffic from N Rosa Rd to Old Sauk Rd. One of the impacts of having active traffic on a road reconstruction project like this one is that this will add a significant amount of time for construction. Vehicular access for the west segment is restricted to local and emergency traffic only until construction is completed by the end of September.

Access to driveways will be interrupted for residential properties when installing concrete features such as curb, sidewalk, and drive approaches to allow concrete to cure and gain strength. Access is always maintained to businesses by requirement of the City when the contractor is installing concrete features adjacent to their property.

After Construction Completion

There will be significant improvements to Old Middleton Rd after construction is finalized. Some of the improvements are:

  • A smooth road surface designed to last 20 years before needing rehabilitation.
  • New underground sanitary sewers that meets the current design standards and can last as long as 80 years.
  • New underground storm sewer that will drain the street efficiently making the street better prepared when bigger rain events fall.
  • New curb and gutter sections that will have sufficient grade to carry runoff water into the new storm sewer drains.
  • New sidewalk sections that will improve the pedestrian network along the street.
  • New pedestrian ramps that will meet current A.D.A. Guidelines and City construction standards.
  • Addition of bicycle facilities in the road that will enhance safety for bicyclists.

If you have questions or concerns regarding this information or the project, please contact Fadi El Musa, the Project Engineer at 608-243-5214 or by email at felmusagonzalez@cityofmadison.com.

 

Additional resources:

Old Middleton Road and Craig Avenue Resurfacing
City of Madison Engineering
https://www.cityofmadison.com/engineering/projects/old-middleton-road-and-craig-avenue-resurfacing
Updated: 08/26/2022

 

 




Email to a friend Email to a friend

Subscribe to Email List

Subscribe to the District 11 – Alder Tishler email list:


By participating on this list the Wisconsin Public Records Laws may subject your email address to disclosure to third parties. By selecting "Yes" you are requesting that we treat your email address that you have provided to this list as confidential and you are also stating that you would not participate in this service if the City is obligated to release your email address to such third party requesters.


Archive

2023
2022
2021
2020
2019
2018
2017

Labels

Budget
Uncategorized

Tags

Absentee Voting  Advisory  Alternate Side of the Street Parking  Assessments  Ballot Drop Boxes  Bike Paths  Black Lives Matter  Brush Pickup  Budget  Bus Rapid Transit  CARES  Census2020  City High  Communications  Comprehensive Plan  Construction  Coronavirus  Crestwood  Crime Prevention  CUNA  Curfew  Development  Disaster Relief  Dog Park  Early in Person Voting  Elections  Emergency  Face Coverings  Fall  Feedback  FEMA  Financial Hotline  Fire Department  Flooding  Food Scrap Recycling  Forward Dane  General  Glen Oaks  Glenway  Green Infrastructure  Hill Farms  Hilldale  Imagine Madison  Inclement Weather  Information  Informational Sessions  Lane Closures  Large Item Pick Up  Leaf Collection  Library  Madison Yards  Mayor  Mayor's Neighborhood Conference  Meeting Schedule  Metro  Midtown Police Station  Midvale Heights  Neighborhood Grants  Neighborhood Meetings  Neighborhood Safety  Online Meeting  Parking  Parks  Plan Commission  Police  Poll Workers  Prescribed BUrns  Presentation  Property Taxes  Public Health  Public Health  Public Hearing  Public Market  Recycling  Redistricting  Redistricting  Reopening  Road Closures  Roads  Safer At Home  Safety  Scams  Schools  Severe Weather  Snow  Solar Panels  Spring  Stormwater  Street Sweeping  Streets  Summer  Sunset Village  Text Alerts  Town Hall  Traffic Enforcement  Traffic Enforcement  Training Sessions  Transit  Transportation  Trash Collection  Tree Removal  University Avenue  Virtual Meeting  Vision Zero  Water  Water Mains  Watershed  Weekly Meeting Schedule  Weekly Update  Westgate  Westgate  Westmorland  Wheel Tax  Wind  Winter  Yard Waste