3400 Block East Washington Ave Sewer Replacement
September 30, 2024 Update
Speedway Sand & Gravel have started work on the sewer replacement project, as of September 26. Work is anticipated to be complete within 4 weeks. Please pay attention to traffic control signals and bicycle route detours.
View past project updates »Project Details
Project Information
Project Overview
The City of Madison is proposing to install new sanitary sewer main and abandon existing sanitary sewer on E Washington Ave, from N Fair Oaks Ave to Reindahl Ave in 2024. The proposed design will provide the necessary sewer capacity for the 958 Rise Ln property, currently in the stage of redevelopment.
Project Limits
E Washington Ave, between N Fair Oaks Ave and Reindahl Ave. Construction will occur in the south eastbound traffic lane.
Project Schedule
The project has a final completion date of Nov. 15, 2024 or 40 calendar days from the start of work, whichever date is earliest. Work may begin as early as Sept. 3, 2024.
City Process, Meetings
Bid Opening, Special: July 18, 2024
Board of Public Works:July 24, 2024
Common Council: Aug. 6, 2024