American Family Lift Station Emergency Generator
October 5, 2026 Update
Quarter 4 2026 Update
Project schedule dates have been updated to:
Construction: October 2025 - June 2027
Project Details
American Family Lift Station
Project Information
Project Overview
Installation of a fixed, onsite emergency generator that will activate and power the lift station in the event of a power failure. Lift stations are critical to ensuring interrupted sanitary sewer service.
Project Schedule
City User Agency: Engineering
Planning and Design: January – May 2024
Construction: October 2025 - June 2027
Project Updates
October 5, 2026 Update
Quarter 4 2026 Update
Project schedule dates have been updated to:
Construction: October 2025 - June 2027