Schedule
Design 2015-2017
Construction 2018

Details
Buckeye Road will be reconstructed from Monona Dr to Stoughton Rd.  Project includes new pavement, curb & gutter, bike lanes, sidewalk replacement as necessary, street lighting, storm sewer, water main and sanitary sewer replacement.

Public Information Meeting
The City held a public information meeting on this project at the Frank Allis Elementary School, 4201 Buckeye Rd, Madison, WI 53716 from 6 to 8pm on Monday April 25, 2016 in the school cafeteria.  The city presented the design, answered questions and gathered public input.  Information from the meeting can be found below: