Last Updated: 06/16/2017

Update

COUNTY HIGHWAY PD

Work this week – Currently in Stage2 Traffic Control

  • Grading for the new westbound McKee Road
  • Rock Blasting operations for the new westbound McKee Road
  • Place concrete for box culvert extension at Muir Field Road

 

Work scheduled for the next week -

  • Grading for the new westbound McKee Road
  • Rock Blasting operations for the new westbound McKee Road
  • Place concrete for box culvert extension at Muir Field Road

 

Traffic impacts -

  • Blasting Rock May 31st through June 16th - EXPECT DELAYS- Traffic will be stopped for short periods.
  • Muir Field Road, 15 day Full Closure, Monday June 12th through June 26th.

Limits
CTH PD (McKee Rd) from CTH M to Maple Grove Rd

Schedule
April 2017 through October 2017

Plans
Cth PD Plans

Proposed Night Work
Some night work is proposed for safety and to minimize inconvenience for traffic.  The details can be found here:  Nightwork CTH PD

Details
The CTH PD project includes reconstruction of CTH PD to a 4 lane divided urban arterial street with bike lanes, curb & gutter, sidewalk and a curbed, grassed median.  Street Lighting, Traffic Signals, Storm sewer, Water Main and Sanitary Sewer are included in the project also.  A pedestrian and bicycle overpass for the Ice Age Junction Path is proposed just west of High Point Road.

Public Information Meetings

Public Information Meeting #1
The City and County held a public information meeting for this project on August 18, 2015 at the Meadowwood Neighborhood Center (5750 Raymond Rd. Madison, WI).  The presentation and plans can be viewed below:
Presentation

Public Information Meeting #2
The City and County are held a 2nd Public Information Meeting on June 9, 2016 at 6:30 PM at Chavez Elementary School (3502 Maple Grove Rd. Madison, WI).  Staff provided a presentation and answered questions about the project.  The presentation and plans can be viewed below:
Presentation
Handout
Plans

Preconstruction Public Information Meeting
The City and County held a preconstruction meeting to discuss the project and what to expect during construction.  The meeting was held on Wednesday April 26, 2017 in the Chavez Elementary School Cafeteria (3502 Maple Grove Dr.).
Notice
Presentation