Fire Station 6 Tenant Build Out
April 8, 2026 Update
Quarter 2 2026 Update
OPN Architects was selected to lead the design team for the Fire Station 6 Tenant Build Out project. OPN Architects coordinates fire station space needs with Potter Lawson, the architecture firm designing the overall CDA development at Park and Badger. The design of the CDA development “core and shell" is slightly ahead of the design on the fire station interior project.
Project Details
Project Information
Project Overview
Fire Station 6 will be relocated to a new space constructed as part of the CDA redevelopment of the site at South Park Street and West Badger Road in South Madison. The Fire Station project will build out the interior space of the new building to create a fire station for a double company with individual sleeping rooms, fitness room, training room, living/dining/kitchen, apparatus bay, and related spaces.
Project Schedule
City User Agency: City of Madison Fire Department
Planning and Design: March 2025
1st Advertisement of Bid: TBD available only on Bid Express
Bid Due Date: TBD
Construction Start Date: TBD
Expected Completion Date: TBD
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations will be indicated below when scheduled.
Project Updates
April 8, 2026 Update
Quarter 2 2026 Update
OPN Architects was selected to lead the design team for the Fire Station 6 Tenant Build Out project. OPN Architects coordinates fire station space needs with Potter Lawson, the architecture firm designing the overall CDA development at Park and Badger. The design of the CDA development “core and shell" is slightly ahead of the design on the fire station interior project.