Library Services and Support Facility Exterior Envelope

January 26, 2026 Update

Quarter 1 2026 Update
Bids for RFB #14089-0-2025-TJ were received and a contract is in process. Work on site is expected to begin this spring and completed by the end of May.

View past project updates »

Project Details

  • Location

    • Library Services and Support Facility
      1301 West Badger Rd
      Madison, WI 53713
  • Project Type

  • Status

    Construction
  • Estimated Schedule

  • Alder District

    • District 18

Library Services and Support Facility

Project Information

Project Overview

Install exterior envelope rain screen to mitigate water intrusion issues at the CMU walls of the existing Library Services and Support Facility located at 1301 West Badger Road.

Project Schedule

City User Agency: Madison Public Library

1st Advertisement of Bid for Construction: December 09, 2025
RFB #14089-0-2025-TJ documents can be found on VendorNet and DemandStar.
"All information regarding dates/times/locations are informational and should be verified with the RFB documents"
Bid Due Date: January 15, 2026 

Construction Start Date: Spring 2026
Expected Completion Date: May 31, 2026
 

Project Updates

January 26, 2026 Update

Quarter 1 2026 Update
Bids for RFB #14089-0-2025-TJ were received and a contract is in process. Work on site is expected to begin this spring and completed by the end of May.

Was this page helpful to you? * required