Mall/Concourse Maintenance Garage Protective Flooring Replacement

This project will be will take place over three weekly phases, removing and replacing the traffic coating at the Mall/ Maintenance garage at 120 S. Fairchild Street.  The work area consists of 7500 square feet of space which houses the City of Madison Mall/Maintenance equipment and workers.


City User Agency: Parks

Project Status: Design
1st Advertisement of Bid: Feb. 5, 2021
Bid Due Date: Feb. 18, 2021
Construction Start Date: May 2021
Expected Completion Date: July 2021