Ohmeda Drive Reconstruction
October 3, 2024 Update
Construction is finishing up on Ohmeda Drive (Femrite Drive to 1,800 feet north). The contractor has completed the sanitary sewer main, laterals, water main, services, storm sewer, and culvert installation. The street grading, curb and gutter, sidewalk, and asphalt paving is also complete along Ohmeda Drive. The Contractor is finishing up pavement marking and soil restoration along Ohmeda Drive as well as asphalt work on Femrite Drive. The project should be complete around mid-October.
View past project updates »Project Details
Project Information
Project Overview
The City is planning to reconstruct Ohmeda Drive off Femrite Drive on the east side of Madison in 2024. The City plans to install sanitary sewer, water main, storm sewer, culverts, stormwater facilities, asphalt, curb and gutter, sidewalk, driveway aprons, street lighting, pavement marking, and signing along Ohmeda Drive. Ohmeda Drive construction is anticipated to begin in spring of 2024 and be completed by fall of 2024.
The new development in the northwest quadrant of the Femrite Drive and Ohmeda Drive intersection is working to install sidewalk and driveways along the north side of Femrite Drive between Interstate 39 and 90 and Ohmeda Drive. All work in this area is anticipated to be complete in the spring of 2024.
Exhibit for proposed layout of Ohmeda Drive
Fact and details sheet
Proposed Assessments
Project Limits
Ohmeda Drive – Femrite Drive to 1,800 feet north, ending at a new cul-de-sac
Project Schedule
Design: Fall 2022/Winter/Spring/Summer/Fall 2023/Winter 2024
Bids Advertised: Spring 2024
Construction Phase: Spring/Summer 2024 to Fall 2024
Public Involvement
The City has met with each property owner along the project to discuss the project scope and answer questions.
Public Information Meetings
No Meeting was held, individual property owners were contacted about the project to discuss impacts.
City Process, Public Hearings
Board of Public Works: November 2, 2022
Common Council: November 22, 2022
Board of Public Works: February 8, 2023
Common Council: February 28, 2023
Board of Public Works: February 7, 2024
Common Council: March 5, 2024
Mailings
Board of Public Works Notice Mailing (includes proposed assessments and fact sheet)
Board of Public Works: Notice, Fact Sheet, Schedule of Assessments (Jan. 23, 2024)
Common Council: Public Hearing Notice (Feb 22, 2024)
Adopted Resolution Notice: Letter, Finance Letter, Resolution, and Assessments (Mar 21, 2024)