Olin-Turville Ct and E. Lakeside Street Resurfacing

October 1, 2024 Update

The contractor has completed street resurfacing and utility work for the southern half of the project on Olin-Turville Ct between the Olin Park boat launch parking lot and the Olin-Turville Ct/John Nolen Dr intersection.  They are now continuing street resurfacing and utility work on the northern half of the project on Olin-Turville Ct and E. Lakeside St between the Olin Park boat launch and E. Lakeside St/John Nolen Dr intersection. 

The contractor will be paving the northern half of the project next week Tuesday, October, 8th.  Access will continue to be maintained to properties and MSCR facilities on E. Lakeside St throughout paving, but some minor delay should be expected as crews work in this area.  Access to the Olin Park boat launch parking lot will remain from the southern Olin-Turville Ct/John Nolen Dr intersection.  After paving is complete, the contractor will be installing pavement markings and completing site restoration.

View past project updates »

Project Details

  • Location

    • 310 E Lakeside St
      Madison, WI 53715
  • Status

    In Design
  • Estimated Schedule

  • Impact

    Major
  • Alder District

    District 13
    District 14
  • Contract Number

Project Information

Project Overview

The purpose of this street project is to resurface the pavement and replace some underground utilities on Olin-Turville Ct from John Nolen Dr to E. Lakeside St and E. Lakeside St from John Nolen Dr to Olin-Turville Ct.  Work includes replacing approximately 0.41-miles of asphalt pavement, replacing concrete curb and gutter, sidewalk, and curb ramps as needed, replacing sanitary sewer main as needed, and storm culvert replacements.  The existing street widths on all streets will remain the same.

Project Limits

Olin-Turville Ct from John Nolen Dr to E. Lakeside St

E. Lakeside St from John Nolen Dr to Olin-Turville Ct

Project Schedule

Design: Spring/Summer 2024

Anticipated Start of Construction: September 2024

Anticipated End of Construction: October 2024

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

June 3, 2024 Public Information Meeting PowerPoint Presentation

June 3, 2024 Public Information Meeting Recording

City Process, Meetings

Common Council: 6/4/2024

Board of Public Works: 5/22/2024

Project Updates