Project Description
This project will remove and replace concrete curb and gutter; remove and replace sidewalk, as needed; remove and replace drive aprons, install a new asphalt pavement; replace sanitary sewer main and laterals; replace the water main; replace storm sewer, as necessary.

Project Limits
Pine St - Beld St to Gilson St

Project Schedule
March 7 - Board of Public Works
March 20 - Common Council
May 29 - Begin Construction