Reindahl Restroom Remodel
Project Details
Project Information
Latest Update
Jan. 31, 2023
The new restrooms at the Reindahl Splashpad are substantially complete. Visit our project Flickr page for construction photos.
Project Overview
Creating two single use restrooms and a small mechanical room within the existing unused concessions space of the mechanical building at the Reindahl Park Splash Pad.
Project Schedule
City User Agency: City of Madison Parks
Planning and Design: January - July 2021
1st Advertisement of Bid: May 26, 2022 available only on Bid Express
Pre-bid Meetings
Wed. June 08, 2022 @ 9:00 a.m. at 1818 Portage Rd., Madison, WI
Tues. June 14, 2022 @ 9:00 a.m. at 1818 Portage Rd., Madison, WI
Bid Due Date: July 14, 2022
Construction Start Date: September 06, 2022
Expected Completion Date: May 05, 2023
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
City Process Meetings
Aug. 02, 2022 Common Council File #72601
July 20, 2022 Board of Public Works File #72601
Awarding Public Works Contract No. 8586, Reindahl Restroom Remodel
June 07, 2021 File #65447
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Reindahl Restroom Remodel