Last Updated: 10/10/2022

Latest Update

10/10/2022 Update:

The contractor has completed installing the underground utilities and reconnecting services for the project.  Installation of concrete driveway aprons and curb and gutter is underway and is expected to be finished by Tuesday 10/11.  After the concrete work is complete, the contractor will begin final landscaping and restoration for the site.  Final asphalt paving of the street is currently scheduled for Thursday 10/20.

Project Overview

The purpose of this project is to reconstruct the street and replace utilities on Russell Street from Winnebago Street to Eastwood Drive.  Proposed work includes replacement of the following: asphalt pavement and road base, curb and gutter, driveway aprons, sidewalk (as needed), water main, sanitary sewer main and laterals, storm sewer and private storm sewer connections.

Project Fact & Details Sheet

Project Limits

Russell Street from Winnebago Street to Eastwood Drive

Project Schedule

Design: Spring 2022
Bid Advertising: May 2022
Start Construction: August 2022
End Construction: October 2022 (Approximate)

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

City Meetings, Process

Common Council: March 15, 2022

Board of Public Works: March 2, 2022

Mailings

Project Fact & Details Sheet
Start Work Letter & Fact Sheet