Russell Street Reconstruction
Latest Update
10/10/2022 Update:
The contractor has completed installing the underground utilities and reconnecting services for the project. Installation of concrete driveway aprons and curb and gutter is underway and is expected to be finished by Tuesday 10/11. After the concrete work is complete, the contractor will begin final landscaping and restoration for the site. Final asphalt paving of the street is currently scheduled for Thursday 10/20.
Project Overview
The purpose of this project is to reconstruct the street and replace utilities on Russell Street from Winnebago Street to Eastwood Drive. Proposed work includes replacement of the following: asphalt pavement and road base, curb and gutter, driveway aprons, sidewalk (as needed), water main, sanitary sewer main and laterals, storm sewer and private storm sewer connections.
Project Limits
Russell Street from Winnebago Street to Eastwood Drive
Project Schedule
Design: Spring 2022
Bid Advertising: May 2022
Start Construction: August 2022
End Construction: October 2022 (Approximate)
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
- Feb. 17, 2022 Public Information Meeting PowerPoint Presentation
- Feb. 17, 2022 Public Information Meeting Recording
City Meetings, Process
Common Council: March 15, 2022
Board of Public Works: March 2, 2022