Update: December 17, 2021

Project Status: Completed
For real time and historical output data for the system please visit these monitoring links:

Completed install of solar photovoltaic system at Madison Fire Department Station 07:

FS07-MPD West Solar


Solar Electric Installation

Installation of a roughly 46 kW solar photovoltaic system at the Madison Fire Department Station 7. The system will be ground mounted modules and will produce an estimated 60,000 kWh per year. The systems production will be split between Station 7 and the Madison Police Department West District Station next door. 25% of MFD Station 7’s and 19% of MPD West District Station’s electricity usage will be generated by the solar arrays. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.


City User Agencies: City of Madison Fire and City of Madison Police

Planning and Design : January – March 2021

1st Advertisement of Bid: N/A

Bid Due Date: N/A

Construction Start Date: April 2021

Expected Completion Date: July 2021