Solar PV - Metro Phase 3
Project Details
Project Information
Project Overview
Installation of a roughly 120 kW solar photovoltaic system at the Metro Transit Facility. The system will be roof mounted modules and will produce an estimated 138,000 kWh per year. When combined with the building’s existing roof mounted system, 35% of the building’s electricity usage will be generated by the solar arrays. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.
Project Schedule
City User Agencies: Metro Transit
Planning and Design : March – July 2021
1st Advertisement of Bid: N/A
Bid Due Date: N/A
Construction Start Date: August 2021
Expected Completion Date: April 2022
Aerial view of solar photovoltaic system on Metro:

Rooftop view of solar photovoltaic system: