Solar PV - Police Training

January 4, 2024 Update

The project is currently in Construction and is expected to be completed in February 2024.

View past project updates »

Project Details

  • Location

    • 5702 Femrite Dr.
      Madison, WI 53718
  • Project Type

  • Status

    Construction
  • Estimated Schedule

  • Alder District

    District 16

Project Information

Project Overview

Installation of a roughly 60 kW solar photovoltaic system at the Madison Police Department Training Center. The system will be a combination of roof mounted and ground mounted modules and will produce an estimated 78,000 kWh per year. When combined with the building’s existing roof mounted system, 35% of the building’s electricity usage will be generated by the solar arrays.  The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.

Project Schedule

City User Agency: Madison Police Dept. 
Planning and Design: Jan – June 2022

Site work for ground mounted modules in early 2022

Construction Start Date: August 2023
Expected Completion Date: February 2024

Project Updates

The project is currently in Construction and is expected to be completed in February 2024.