South Park Street Concrete Pavement Repairs

Last Updated: 01/07/2021

Project Update

1/4/2021 Update:
Thank you for everyone who attended the Jan. 4, 2021 public information meeting for this project.
 

Jan. 4, 2021 Public Information Meeting Recording

Jan. 4, 2021 Public Information Meeting PowerPoint Presentation

Plans and Specifications and authorizing the Board of Public Works to advertise the project were be presented at the Jan. 6, 2021 BPW meeting.

Project Overview

This is a concrete pavement replacement project for the southbound lanes only.  This is a continuation of the 2019 Concrete pavement replacement project for the northbound lanes of South Park. The contractor will replace transverse, longitudinal joints and concrete pavement that is in poor condition for the southbound lanes of South Park Street.

South Park Street Fact Sheet

Project Limits

South Park Street:  West Badger Road to the Railroad Crossing and from West Olin Avenue to West Washington Avenue

Project Schedule

Approving Plans Specifications: January 6, 2021
Bid Advertisement: February 4, 2021
Start of Construction: May 2021
End of Construction: August 2021

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

Jan. 4, 2021 Public Information Meeting PowerPoint Presentation
Jan. 4, 2021 Public Information Meeting Recording

City Process, Meetings

Board of Public Works: Jan. 6, 2021
Common Council: Jan. 19, 2021