Last Updated: 12/05/2017

New Restrooms/Shelter

Replacing the restroom building at Olbrich Park (Walter Street location).


City User Agency:  Parks Division
Design and Planning: Fall 2017
1st Advertisement of Bid: January 2018
Bid Due Date: TBD
Construction Start Date: June 2018
Expected Completion Date: December 2018


New Restroom/Shelter Rendering

(subject to change during the next phase of the design process)
Walter St Restrooms


Project History:

Oct. 12, 2017  Public Meeting
Exhibits presented at the meeting can be found HERE