Survey of the project area is currently being obtained by City survey staff. After this data is obtained, design of the sanitary sewer can be finalized. Concurrently, the project will be heading through approvals with BPW and CC in the coming weeks.

View past project updates »

Project Details

  • Location

    • Address Location: 601 West Dayton Street
      Madison, WI 53703
  • Status

    In Design
  • Estimated Schedule

  • Impact

    Minor
  • Alder District

    • District 4
    • District 8
  • Contract Number

Project Information

Project Overview

The existing sanitary sewer mains will be replaced and upsized on West Dayton Street between North Lake Street & North Frances Street. The existing sanitary sewer is 18” clay and was installed in 1931. The new sewer will be 24” PVC. Within these replacement limits, existing sanitary sewer laterals will be reconnected into the new sanitary sewer main(s).  However, it is expected that all connected existing sanitary sewer laterals are made of PVC and in such condition that replacement of existing laterals is not necessary.

The City will coordinate this work with nearby UW-Madison facilities such that impacts to traffic, UW-events, etc. are minimized by this project. 

Project Limits

West Dayton Street between North Lake Street & North Frances Street

Project Schedule

Design: Spring/Summer 2025

Anticipated Bid Date: Fall 2025

Construction Timeframe: Spring/Summer/Fall 2026

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

A public information meeting will not be held for this project given that impacts are limited to the one block of West Dayton Street between N Lake St. & N Frances St.

City Process, Meetings

 

Project Updates

June 2, 2025 Update

Survey of the project area is currently being obtained by City survey staff. After this data is obtained, design of the sanitary sewer can be finalized. Concurrently, the project will be heading through approvals with BPW and CC in the coming weeks.