August 25, 2025 Update
Survey of the project area has been obtained by City staff and the design of the new sewer along W. Dayton St is nearly complete. We are now verifying with private utilities and UW-Madison that the design is suitable given their facilities in the area. The project is still slated to be bid at the end of September with construction slated for next Spring/Summer (2026).
View past project updates »Project Details
Project Information
Project Overview
The existing sanitary sewer mains will be replaced and upsized on West Dayton Street between North Lake Street & North Frances Street. The existing sanitary sewer is 18” clay and was installed in 1931. The new sewer will be 24” PVC. Within these replacement limits, existing sanitary sewer laterals will be reconnected into the new sanitary sewer main(s). However, it is expected that all connected existing sanitary sewer laterals are made of PVC and in such condition that replacement of existing laterals is not necessary.
The City will coordinate this work with nearby UW-Madison facilities such that impacts to traffic, UW-events, etc. are minimized by this project.
Project Limits
West Dayton Street between North Lake Street & North Frances Street
Project Schedule
Design: Spring/Summer 2025
Anticipated Bid Date: Fall 2025
Construction Timeframe: Spring/Summer/Fall 2026
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
A public information meeting will not be held for this project given that impacts are limited to the one block of West Dayton Street between N Lake St. & N Frances St.
City Process, Meetings
- Common Council 7/1/2025
- Board of Public Works 6/18/2025