Project Overview

Installation of a fixed, onsite emergency generator that will activate and power the station in the event of a power failure. 

Project Schedule

City User Agency: Madison Police Department

Planning and Design: January – April 2026

Construction: November 2026 - June 2027

Project Updates

October 5, 2026 Update

Quarter 4 2026 Update
Project schedule dates have been updated to:
Construction: November 2026 - June 2027