Willows Biobasin Repair

June 23, 2026 Update

This project is currently in the design phase of development. 

View past project updates »

Project Details

Location

10012 Elderberry Rd
Madison, WI 53562

Status

In Design

Estimated Schedule

Impact

Minor

Alder District

  • District 9

Contract Number

Project Information

Project Overview

This project improves drainage within the 528-548 Burnt Sienna Drive. These improvements include

  • Replacing the 18" storm pipe with a swale, which has a larger volume capacity. 
  • Adding to twin 18" pipes under the existing path to convey the 100-year storm event.
  • Lowering the existing bike path to accommodate stormwater in events greater than the 100-year storm event. 

Project Limits

Example: 528-548 Burnt Sienna Drive

Project Schedule

Construction Anticipated to Begin in late fall 2026.

Public Involvement

City Process, Meetings

Common Council 7/21/2026

Board of Public Works 7/8/2026

Project Updates

June 23, 2026 Update

This project is currently in the design phase of development. 

Was this page helpful to you? * required