Project Information
Update: October 12, 2020
Photos added for delivery and setting of the pre-fab building on-site. See action photos below!
New Radio and Equipment Shelter
City User Agency: Traffic Engineering
Project Status: Construction!
Construction Start Date: August 2020
Expected Completion Date: October 2020
Construction Progress
July 08, 2020: Staking the site for construction of the footings and foundation:
August 09, 2020: Forming for the footings:
August 17, 2020: Foundation and grading completed and waiting for the shelter to be delivered:
Sept. 24, 2020: The pre-fab building is complete and ready to ship to the project site:
Oct. 08, 2020: Delivery to the site:
October 9, 2020 Setting the pre-fab building at the site: