Mall/Concourse Maintenance Protective Flooring Replacement
Archived Project
This project is complete. This information is available for reference.
If you need an accessible version of this
content, please report an accessibility
issue.
Project Details
Project Information
March 22, 2021 Update:
Project Status: CONSTRUCTION!
Project History
March 22, 2021 File #64354
Awarding Public Works Contract No. 9429, Mall/Concourse Maintenance Protective Flooring Replacement
Mall/Concourse Maintenance Garage Protective Flooring Replacement
This project will be will take place over three weekly phases, removing and replacing the traffic coating at the Mall/ Maintenance garage at 120 S. Fairchild Street. The work area consists of 7500 square feet of space which houses the City of Madison Mall/Maintenance equipment and workers.
City User Agency: Parks
Project Status: Construction
1st Advertisement of Bid: Feb. 5, 2021 available on Bid Express
Bid Due Date: Feb. 18, 2021
Construction Start Date: April 12, 2021
Expected Completion Date: July 01, 2021
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Project History
March 22, 2021 File #64354
Awarding Public Works Contract No. 9429, Mall/Concourse Maintenance Protective Flooring ReplacementJanuary 25, 2021 File #63531
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Mall/Concourse Maintenance Protective Flooring Replacement